Monday, October 26, 2015

Phase I: Main Line Work Completed. Phase II: Lining On-Going

Phase I: Glenview Road to Eastwood Lane
Work Completed Last Week
·         Completed open cut installation of connection points
·         Installation of new fire hydrants
·         Fill lined water main with water.

 Work Anticipated This Week:
·         Perform necessary testing and receive required approvals prior to reconnecting homes to new water main.

Phase II: Eastwood Lane to Appletree Lane
Work completed Last Week:
·         Shut-down existing 12-inch water main
·         Began televising and cleaning existing water main
·         Began installing internal liners

Work Anticipated This Week:
·         Complete televising and cleaning existing water main
·         Complete installing internal liners
·         Perform pressure testing of internal liners
·         Begin open water main installation at connection points
·         Begin installing new fire hydrants.

Minimal work along Phase I will occur this coming week due to performing the necessary testing and acquiring needed approvals prior to reconnecting homes to the new lined water main. Once all approvals are received, the permanent water service connections will be completed and the temporary water main will be removed in Phase I.

The internal lining of the existing water main along the entire project site is expected to be completed by the end of next week.

Thank you again for all your patience and understanding.

Monday, October 19, 2015

Open Cut Water Main on Phase I. Start Internal Lining of Phase II

Phase I: Glenview Road to Eastwood Lane

Work Completed Last Week
·         Pressure testing and televising of internal liner
·         Reinstated water services within internal liner
·         Installation of connection points and fire hydrants

Work Anticipated This Week:
·         Complete open cut installation of connection points and fire hydrants
·         Complete televising of internal liner
·         Complete reinstating water services within internal liner
·         Chlorinate and testing of new internal liner 

Phase II: Eastwood Lane to Appletree Lane

Work completed Last Week:
·         Installation of new 12-inch water valve at Appletree Lane
·         Excavation of pits for installing internal liner.

Work Anticipated This Week:
·         Shut-down existing 12-inch water main for lining.
·         Televising and cleaning of existing 12-inch water main
·         Install internal liner within existing 12-inch water main

We appreciate all the patience and understanding of the residents along Wagner Road and the surrounding neighborhoods dealing with travel delays and water main shut downs over the past few weeks. There will be additional water shut downs throughout at the area as work continues. Residents will be notified 24-hours in advance of any scheduled shut-down, but please be aware, there are occasions the water main needs to be turn off to make an emergency repair.

Monday, October 12, 2015

Phase I Lining Started. Provided Temporary Water Service for Phase II

Phase I: Glenview Road to Eastwood Lane
Work Completed Last Week
·         Open cut water main installation at Eastwood lane
·         Cleaning and televising of existing 12-inch water main
·         Installed internal liners within existing 12-inch water main
·         Started performing pressure testing for internal lining.

Work Anticipated This Week:
·         Complete pressure testing of internal liners
·         Make connections of internal liner segments
·         Install fire hydrants
·         Reinstate services within internal liner 

Phase II: Eastwood Lane to Appletree Lane
Work completed Last Week:
·         Transferred existing water services currently on the existing 12-inch water main to existing 6-inch water main to allow for temporary water service during the lining process.
·         Started excavating for boring pits

Work Anticipated This Week:
·         Complete excavating boring pits
·         Install new valve at Apple Tree Lane
·         Turn-Off existing 12-inch water main
·         Begin cleaning and televising existing 12-inch water main in preparation for internal lining

Monday, October 5, 2015

Water Main Lining in Phase I Started

Phase I: Glenview Road to Eastwood Lane
Work Completed Last Week
·         Completed excavation for boring pits
·         Connected all homes to temporary water main
·         Installation of new valve at Green Acres
·         Began open cut installation of water main at Eastwood Lane
·         Began cleaning and televising existing 12-inch water main

Work Anticipated This Week:
·         Complete open cut installation of water main at Eastwood Lane
·         Continue cleaning and televising of existing 12-inch water main.
·         Begin installation of internal liner in existing 12-inch water main.

Thank you to all those residents along Phase I who cooperated with construction operations and contacting the contractor to get your temporary water service hooked-up.

Phase II: Eastwood Lane to Appletree Lane
Work completed Last Week:
·         No work completed.

Work Anticipated This Week:
·         Begin Excavating Boring Pits
·         Transferring existing water services currently on the existing 12-inch water main to existing 6-inch water main to allow for temporary water service during the lining process.