Tuesday, November 3, 2015

Internal Lining Installation Completed. Open Cut Water Main On-Going.

Phase I: Glenview Road to Eastwood Lane
Work Completed Last Week
·         Performed necessary testing and requested required approvals prior to reconnecting homes to newly lined water main.

Work Anticipated This Week:
·         Receive required approvals based on test results
·         Start re-establishing / installing new water services to each home

Once the water service is re-established or a new water service is installed outside your home, the contractor and Village of Glenview will need to enter your home to reconnect the service inside the house. The Village of Glenview will be installing new water meters at the same the connection is made. Once this connection is made, you will no longer be serviced from the temporary water main. The contractor will be contacting you to schedule appointments to enter your home. Please make every effort to respond to their requests in order to get your service reconnected as quickly as possible.

Thank you in advance for all your cooperation and patience.

Phase II: Eastwood Lane to Appletree Lane
Work completed Last Week:
·         Installed internal liners
·         Performed pressure testing on internal liner
·         Performed cleaning and televising of internal liner
·         Performed open cut installation of water main between liner segments

Work Anticipated This Week:
·         Continue with open cut installation of water main between liner segments
·         Install fire hydrants
·         Begin testing prior to placing lined water main into service.

The installation of the internal liner within the existing water main is now completed for the entire project.