Monday, October 5, 2015

Water Main Lining in Phase I Started

Phase I: Glenview Road to Eastwood Lane
Work Completed Last Week
·         Completed excavation for boring pits
·         Connected all homes to temporary water main
·         Installation of new valve at Green Acres
·         Began open cut installation of water main at Eastwood Lane
·         Began cleaning and televising existing 12-inch water main

Work Anticipated This Week:
·         Complete open cut installation of water main at Eastwood Lane
·         Continue cleaning and televising of existing 12-inch water main.
·         Begin installation of internal liner in existing 12-inch water main.

Thank you to all those residents along Phase I who cooperated with construction operations and contacting the contractor to get your temporary water service hooked-up.

Phase II: Eastwood Lane to Appletree Lane
Work completed Last Week:
·         No work completed.

Work Anticipated This Week:
·         Begin Excavating Boring Pits
·         Transferring existing water services currently on the existing 12-inch water main to existing 6-inch water main to allow for temporary water service during the lining process.