Monday, October 26, 2015

Phase I: Main Line Work Completed. Phase II: Lining On-Going

Phase I: Glenview Road to Eastwood Lane
Work Completed Last Week
·         Completed open cut installation of connection points
·         Installation of new fire hydrants
·         Fill lined water main with water.

 Work Anticipated This Week:
·         Perform necessary testing and receive required approvals prior to reconnecting homes to new water main.

Phase II: Eastwood Lane to Appletree Lane
Work completed Last Week:
·         Shut-down existing 12-inch water main
·         Began televising and cleaning existing water main
·         Began installing internal liners

Work Anticipated This Week:
·         Complete televising and cleaning existing water main
·         Complete installing internal liners
·         Perform pressure testing of internal liners
·         Begin open water main installation at connection points
·         Begin installing new fire hydrants.

Minimal work along Phase I will occur this coming week due to performing the necessary testing and acquiring needed approvals prior to reconnecting homes to the new lined water main. Once all approvals are received, the permanent water service connections will be completed and the temporary water main will be removed in Phase I.

The internal lining of the existing water main along the entire project site is expected to be completed by the end of next week.

Thank you again for all your patience and understanding.