Phase I Lining Started. Provided Temporary Water Service for Phase II

Phase I: Glenview Road to Eastwood Lane
Work Completed Last Week
·         Open cut water main installation at Eastwood lane
·         Cleaning and televising of existing 12-inch water main
·         Installed internal liners within existing 12-inch water main
·         Started performing pressure testing for internal lining.

Work Anticipated This Week:
·         Complete pressure testing of internal liners
·         Make connections of internal liner segments
·         Install fire hydrants
·         Reinstate services within internal liner 

Phase II: Eastwood Lane to Appletree Lane
Work completed Last Week:
·         Transferred existing water services currently on the existing 12-inch water main to existing 6-inch water main to allow for temporary water service during the lining process.
·         Started excavating for boring pits

Work Anticipated This Week:
·         Complete excavating boring pits
·         Install new valve at Apple Tree Lane
·         Turn-Off existing 12-inch water main
·         Begin cleaning and televising existing 12-inch water main in preparation for internal lining