Friday, September 11, 2015


Work Completed Last Week:

·         Mobilize equipment and personnel along with miscellaneous preparation work prior to starting construction.
·         Begin performing the open cut areas of the water main replacement.
·         Begin setting up temporary water main.
·         Temporary water main chlorination.

 
Work Anticipated This Week:
 
     ·         Continue performing the open cut areas of the water main replacement.
     ·     Water sampling and testing.
     ·      Connect existing water services to temporary water main.
     ·      Temporary shutdown of the existing water main on Green Acres Ln. for a water main connection.

Please note, only those houses that were notified will be connected to the temporary water main.  All other houses will remain connected to an existing water main and will be notified of any water main work that will effect your water.
 