Monday, September 28, 2015

Temporary Water Service Being Connected. Begin Water Main Lining Process This Week.

Phase I: Glenview Road to Eastwood Lane
Work Completed Last Week
·         Tested and received required approvals to place temporary water main in service
·         Connected homes to temporary water main to provide service during construction
·         Installed cross-connection between existing water mains at east end of Green Acres Lane
·         Excavation of boring pits

Work Anticipated This Week:
·         Complete excavation of boring pits
·         Connect all homes to temporary water main
·         Turn off existing water main along Wagner Road, scheduled for Wednesday
·         Begin cleaning and televising existing water main along Wagner Road
·         Excavation and installation of new water main at intersection of Wagner Road and Eastwood Lane

Thank you to all those residents along Phase I who cooperated with construction operations and contacting the contractor to get your temporary water service hooked-up.

Phase II: Eastwood Lane to Appletree Lane
Work on Phase II will begin once Phase I is nearly completed.